Yesterday, the German fabricator for the central piece of equipment, the gasifier, told us zur holle fahren and rejected our purchase order telling us that the shop was filled with other work. Now, we are talking about a half a million Euros, give or take. This fabricator was selected because they had already built one of these for another project and this was going to be a duplicate of that one. Easy Peezy. And they turn it down while the purchase order was being typed and we were writing the check for the down payment.
Next is Phase 4: Search for Guilty. Now, WHO exactly decided to use that German shop?
No comments:
Post a Comment